Peppermint Junction work extended for three weeks

Work under way at Peppermint junction of A17 and A151 Holbeach
Work under way at Peppermint junction of A17 and A151 Holbeach
0
Have your say

Traffic management on the A151 in Holbeach, part of the Peppermint Junction improvement scheme, will be extended by three weeks so necessary utility diversions can be completed and final road surfacing can be laid.

Works on the A151 are now expected to be completed on Monday, September 25, subject to reasonable weather conditions.

Senior project leader Sam Edwards said: “An issue with the location and depth of electrical cables under the A151 means we cannot safely carry out construction works in this area without the risk of serious injury or severing power to the nearby area. As a result, the utility company will need to divert the cables so that we can complete the remainder of the construction works.

“Unfortunately, the utility company’s records didn’t identify the exact location of these cables and, therefore, provisions had not been made in the scope of the original closure period.”

To minimise the impact of these additional works and to ensure the road opening on September 25, the contractor will be working additional hours over the coming weekends. Access to businesses and residences will be maintained throughout the works.

Following the extended closure, temporary two-way traffic signals will be in operation (when required) from Monday September 25 to Friday October 13, including weekends, while the contractor completes drainage and surfacing works.

The signed diversion route for the full closure will continue to be via the A151 to the A16 to the A17.

Cllr Richard Davies, executive member for highways, said: “By extending works on the A151 for an extra three weeks, we can ensure the safety of the workforce carrying out the improvements while also eliminating the risk of power loss in the area. In addition, we’ll also take the opportunity to lay the final layer of tarmac over a majority of the road rather than using a temporary surface and surface the majority of the footways along the A151.

“This will result in reducing the number of nights required for full road closures later in the year which will alleviate the traffic congestion this causes in advance of the Christmas period.

“We apologise for any inconvenience this may cause and ask for your continued patience as we carry out these necessary works ahead of the Peppermint Junction improvement scheme coming to an end early next year.”

The £4.8m Peppermint Junction improvement scheme will improve the safety of the current A17/A151 junction by installing a new, three-arm roundabout, as well as a new four-arm roundabout on the A151. The scheme will also provide access to residential land to the east of the A151 and open up development land to the west of the A151 for the creation of Peppermint Park, Holbeach: A Food Enterprise Village, which will include a Food Enterprise Zone (FEZ) and the delivery of approximately 900 new dwellings.

For the latest news on the Peppermint Junction improvement scheme, visit www.lincolnshire.gov.uk/majorprojects.